01 / Miami, FL
Luxury Residential
A roughly $100M, 400-unit project was entitled for 400 units, but the original parking plan could support only about 340. Ownership was struggling to secure financing.
Team members helped replace six three-story garden-style buildings with two additional towers of up to 12 floors. The revised approach reduced foundation costs and freed site area for parking, supporting the full entitled unit count.
Before and after| Measure | Before | After |
|---|
| Units supported by parking | About 340 | 400 entitled units |
|---|
| Estimated project cost | About $100M | About $100M |
|---|
| Estimated value | About $115M | About $130M |
|---|
Result: Estimated value increased by about $15M at the same project cost, and financing became easier to secure.
02 / Miami, FL
Office Tower
A tower design included redundant circulation on each of four floors, limiting sellable space.
Team members identified about 750 square feet per floor that could become sellable space, valued at around $1,300 per square foot. They also improved parking capacity and identified similar-quality finishes at lower cost.
Before and after| Measure | Before | After |
|---|
| Sellable area | Original floor plans | About 3,000 SF added |
|---|
| Estimated value | About $90M | About $96M |
|---|
| Estimated cost | About $70M | About $71M |
|---|
| Estimated profit | About $20M | About $25M |
|---|
Result: Estimated project profit increased by roughly $5M after accounting for the change in cost.
03 / North Port, FL
Multifamily
A 50-unit project had an estimated cost of about $18M against a completed value of about $19M and was not financially viable as planned.
Team members standardized units into modular components and helped redesign the building around them. Moving the gym, leasing office, and amenities into the main building avoided about $1.5M in standalone structures; rentable storage was added. They then led bidding and negotiation, bringing proposals about 20% below the originals.
Before and after| Measure | Before | After |
|---|
| Units | 50 | 50 |
|---|
| Estimated cost | About $18M | About $12.5M |
|---|
| Estimated completed value | About $19M | About $19M |
|---|
Result: Estimated cost fell by about $5.5M, roughly 30%, with completed value unchanged.
04 / San Francisco Bay Area, CA
Large-Scale Mixed-Use
On a large master-planned development, consultant and contractor agreements with major national firms were reviewed and negotiated directly.
Team members negotiated the proposed agreements within 90 days, comparing proposed terms against the revised contract amounts.
Before and after| Measure | Before | After |
|---|
| Consultant and contractor agreements | About $29M proposed | About $24.5M negotiated |
|---|
| Estimated difference | Baseline proposals | About $4.5M |
|---|
Result: The negotiated amounts represented estimated savings of about $4.5M, roughly 15%, compared with the original proposals.