About $30M saved or added across four projects

Examples of value engineering, development strategy, and commercial negotiation across complex projects.

Led by PVA team members before PVA was formed. Figures are estimates.

Request a project review

01 / Miami, FL

Luxury Residential

A roughly $100M, 400-unit project was entitled for 400 units, but the original parking plan could support only about 340. Ownership was struggling to secure financing.

Team members helped replace six three-story garden-style buildings with two additional towers of up to 12 floors. The revised approach reduced foundation costs and freed site area for parking, supporting the full entitled unit count.

Before and after
MeasureBeforeAfter
Units supported by parkingAbout 340400 entitled units
Estimated project costAbout $100MAbout $100M
Estimated valueAbout $115MAbout $130M

Result: Estimated value increased by about $15M at the same project cost, and financing became easier to secure.

02 / Miami, FL

Office Tower

A tower design included redundant circulation on each of four floors, limiting sellable space.

Team members identified about 750 square feet per floor that could become sellable space, valued at around $1,300 per square foot. They also improved parking capacity and identified similar-quality finishes at lower cost.

Before and after
MeasureBeforeAfter
Sellable areaOriginal floor plansAbout 3,000 SF added
Estimated valueAbout $90MAbout $96M
Estimated costAbout $70MAbout $71M
Estimated profitAbout $20MAbout $25M

Result: Estimated project profit increased by roughly $5M after accounting for the change in cost.

03 / North Port, FL

Multifamily

A 50-unit project had an estimated cost of about $18M against a completed value of about $19M and was not financially viable as planned.

Team members standardized units into modular components and helped redesign the building around them. Moving the gym, leasing office, and amenities into the main building avoided about $1.5M in standalone structures; rentable storage was added. They then led bidding and negotiation, bringing proposals about 20% below the originals.

Before and after
MeasureBeforeAfter
Units5050
Estimated costAbout $18MAbout $12.5M
Estimated completed valueAbout $19MAbout $19M

Result: Estimated cost fell by about $5.5M, roughly 30%, with completed value unchanged.

04 / San Francisco Bay Area, CA

Large-Scale Mixed-Use

On a large master-planned development, consultant and contractor agreements with major national firms were reviewed and negotiated directly.

Team members negotiated the proposed agreements within 90 days, comparing proposed terms against the revised contract amounts.

Before and after
MeasureBeforeAfter
Consultant and contractor agreementsAbout $29M proposedAbout $24.5M negotiated
Estimated differenceBaseline proposalsAbout $4.5M

Result: The negotiated amounts represented estimated savings of about $4.5M, roughly 15%, compared with the original proposals.