GMP

A guaranteed maximum price, or GMP, is a contract arrangement that sets a ceiling on the amount payable for defined construction work, subject to the contract's terms and adjustments. The stated maximum is meaningful only alongside its scope, exclusions, allowances, contingency treatment, and rules for changes. It is not automatically a fixed price for every possible project condition. The agreement may also define how savings, reimbursable costs, and supporting records are handled. Owners should read the commercial terms together with the drawings, specifications, schedule, and exhibits that describe the work.

Context

Why it matters

A headline maximum can give a misleading sense of certainty when significant work is excluded, allowances are unresolved, or assumptions do not match the design. Understanding how each component is treated lets the owner identify where cost exposure remains.

The contract's administration rules shape later decisions as much as the initial price. Clear processes for documenting costs, approving changes, and reconciling open items support informed oversight during construction.

At the table

Questions for the owner

  • 01Does the GMP scope correspond to the current design documents and a clear scope narrative? List exclusions, qualifications, alternates, owner-provided items, and unresolved interfaces, then assign responsibility for each gap.
  • 02How are allowances, contingency, fees, and reimbursable costs defined and tracked? Confirm who may authorize their use, what backup is required, whether unused amounts affect the final price, and how changes to assumptions are documented.
  • 03What events permit adjustment to the maximum, and what notice, substantiation, and approval steps apply? Have the project team and legal counsel review the agreement and exhibits together; this glossary provides general information, not legal advice.